In order to further strengthen the construction of industrial gold market management, promotion of "People's Republic of China Tendering" In the gold sector, establish a unified, open, competitive and orderly market building, to ensure speed of construction and construction quality gold projects in To improve the investment efficiency of construction projects and achieve the goal of “ investment province, short cycle, good quality and good efficiency †: the gold bureau of the State Economic and Trade Commission, combined with the actual situation of the current gold industry project construction, on the basis of extensive solicitation of opinions, The Regulations on the Registration and Management of Professional Construction Teams for Gold Industry Engineering Construction was revised. The regulations are as follows:
First, in order to meet the needs of deepening reform and building a socialist market economic system, further strengthen the management of gold industrial engineering construction, promote the implementation of the "Tendering and Bidding Law of the People's Republic of China" in the gold industry, and ensure the construction progress and construction quality of construction projects. These regulations are formulated to improve the investment efficiency of construction projects and achieve the construction goals of “ saving investment, short cycle, high quality and good efficiency †.
2. Any professional construction enterprise or team that intends to undertake the construction of a gold industrial project; an application submitted by the unit and approved by the competent department may apply for a construction permit for the construction of a gold industrial project.
3. The professional construction team refers to the construction team that undertakes the tasks of the mine engineering, the gold mining ship, the mining construction and equipment installation, the large earthwork (including the open-air stripping, the tailings dam) and the mining and mining operation contracting of the gold industrial engineering construction.
4. When applying for a construction permit for a gold project (hereinafter referred to as the “ License †), the following information must be submitted:
1 . A copy of the business license of the construction unit and the legal representative (provided a copy).
2. Corporate assets (fixed assets and working capital) and equipment.
3. Construction management main technical strength status ( professional technical name, level, quantity ) .
4 . The construction situation and quality assessment of the tasks undertaken in the past three years (the project indicates the construction site, the contracting method, the completed investment amount and the first pass rate of the project, and the ratio of excellent rate).
5 . The main economic benefits of the company in the past three years.
6. The address, postal code, and telephone number of the company's location.
5. The construction permit can be applied for by individual project, as well as mine construction and installation, mine roadway engineering, mining and mining operation contracting, etc. It can also be applied for comprehensive construction, but it must not exceed the construction scope and grade approved by the copy of the business license.
6. If the branch or the engineering office of the construction enterprise undertaking the construction of the gold project has independent construction capacity and economically implements independent accounting, the license shall be handled separately.
7. After applying for the approval of the construction permit, the registration fee and the inspection fee must be paid according to the regulations. The charging standards are 600 yuan/time and 500 yuan/time respectively.
8. The construction permit is the basic condition for each construction unit to undertake construction tasks and participate in project recruitment and bidding in the gold industry. The construction unit must issue its permit when undertaking the gold project construction task and participating in the bidding and bidding. Except for the Gold Administration of the State Economic and Trade Commission, other administrative departments may not issue construction permits.
9. The Gold Administration of the State Economic and Trade Commission will regularly announce professional construction teams that have obtained construction permits in the industry.
X. The professional construction team participating in the construction of the gold project must consciously accept the inspection and supervision of the gold construction management departments at all levels, and consciously accept the inspection and supervision of the gold industry quality supervision station and the supervision department, and submit the gold authorities to the project site by the year. Reporting the completion of the construction tasks during the period, and submitting the construction contracting contract signed by the local gold authorities, the construction unit or the enterprise that issued the contract to the State Administration of Economic Affairs, and the Construction and Coordination Office of the Gold Economic Administration of the State Economic and Trade Commission for the record.
11. The construction permit shall be reviewed once every two years, and a special seal for the qualification approval of the gold project shall be affixed. If a professional construction team that has obtained a construction permit fails to participate in the review on time, it shall be deemed to have voluntarily renounced and notified of the cancellation.
12. Actively support and help professional construction teams with good reputation and strong ability to undertake key gold construction projects. Construction teams with poor construction reputation, project delays or major quality accidents will be notified of criticism and economic penalties until they cancel their participation in the construction of gold projects.
thirteen. For construction enterprises and units that do not participate in the qualification certification of gold construction and construction, they will be subject to economic punishment, and the amount of punishment will be 3%-5% of the amount of the task. Any gold competent department and construction unit shall select construction enterprises or units that have not obtained the license, and all the consequences arising therefrom shall be borne by the selected unit.
fourteen. The construction permit for the construction of the gold project shall not be altered, transferred or borrowed. Upon discovery, the certificate will be withdrawn and its qualifications will be cancelled. If there is any loss or loss in the construction permit of the gold project, the license-issuing unit shall promptly report to the issuing authority, affirm the situation, and issue a new certificate after verification.
15. The regulations apply to all enterprises participating in the construction of gold projects and engineering units undertaking the contracting of mining operations.
16. These regulations shall be formally implemented as of the date of promulgation.
17. These Provisions shall be interpreted by the Gold Administration of the State Economic and Trade Commission.